SNEPCo’s Bonga FPSO completes 2022 Turnaround Maintenance (TAM)

Fri, Nov 18, 2022
By editor
1 MIN READ

Oil & Gas

SHELL Nigeria Exploration and Production Company Limited (SNEPCo) is pleased to announce that the 2022 Turnaround Maintenance (TAM) of the Bonga floating production storage and offloading vessel (FPSO)  has been completed.

The 225kbopd capacity FPSO was shut down on October 18, 2022 to carry out statutory inspections, recertfications and other critical asset integrity restoration activities.

The 2022 TAM which was originally planned for 30 days was completed in 22 days on November 9, 2022 thanks to excellent front-end planning and flawless execution. 

Commissioning and start-up activities are in progress and will culminate in ramp up of oil and gas production in the coming days.